Scope of Works:

  • Site formation and ELS works including 300 nos. of pipe pile with 219mm dia. and grout curtain, excavation and shoring installation
  • Slope upgrading works
  • Drainage works

Contract Sum:

  • $39.1M

Contract Period:

  • March 2015 – November 2016

The project involves site formation works with large volume of rock. Different methods are adopted for rock breaking works like mechanical rock splitter and chemical expansion method. Liaise with LCSD for tree felling issue. The project was implemented with environmental requirement of HK BEAM Plus.