N.K.I.L. 6584, OFF SIN FAT ROAD, KWUN TONG
茜發道
項目摘要

工程範圍:

  • Site formation and ELS works including excavation and shoring installation
  • Footing & pile cap construction works
  • Underground drainage works

工程總額:

  • $306M

合約工期:

  • January 2018 to October 2019

此地盤為住宅發展項目,擬興建7座26層以上的住宅,1至2層的地下室。由於此地點位於復修堆填區附近,因此實施了特別的安全措施。該專案已執行HK BEAM Plus的環保要求。

快照
Sin Fat Road
Sin Fat Road
Sin Fat Road
Progress at 20180220-01
Progress at 20180220-02
Progress at 20180220-03
Progress at 20180220-04
Progress at 20180220-05
Progress at 20180220-06
Progress at 20180220-07
Progress at 20180220-08
Progress at 20180220-09
Sin Fat Road
Sin Fat Road
Sin Fat Road
Sin Fat Road
Sin Fat Road
Sin Fat_19.3.19_01
Sin Fat_19.3.19_02
Sin Fat_19.3.19_03
Sin Fat_19.3.19_04
Sin Fat_19.3.19_05
Sin Fat_19.3.19_06
Sin Fat_19.3.19_07
Sin Fat_19.3.22_01
Sin Fat_19.3.22_02
Sin Fat_19.3.22_03
20190806 (7)
3e8769cb-bc1d-465f-8b32-d345ae46e9fb
00b6c1bd-01b2-4efc-8636-66366722bf74
2019-12-17 at 15.10.58
2019-12-17 at 15.12.38